Warning: Invalid argument supplied for foreach() in /home/be2018/sunriseenterprisebd.com/wp-content/plugins/unyson/framework/helpers/general.php on line 1275

Portfolio

Ghorashal (unit-04) 400 MW repowering work

The key activity of the proposed Project is to convert Unit 4, one of the four
210 MW gas-fired steam units at Ghorashal Power Station (GPS), into a combined
cycle unit for an upgraded total capacity of about 400 MW+/-10%. The steam unit is
currently generating 170MW and the overall efficiency of the unit is around 31%. The
proposed Project would increase the overall efficiency of the unit to 54% and the
generation output will also be more than doubled with only 18% increase in gas
requirement. Fuel consumption (per GWh) would be reduced by 44%, which would
also lead to lower greenhouse gas emissions.

Categories